At 11:06 a.m. on December 22, CR Tianzhen's 20MWp photovoltaic power generation project was formally incorporated into the power grid. This is CR Power's first photovoltaic power generating project. It filed the document (Jin Fa Gai Bei An [2015] No. 174) with the Shanxi Provincial Development and Reform Commission on August 3, 2015, and was under construction for 126 days from August 18, 2015, to December 22, 2015, when it was incorporated into the power grid.
The China Resources Tianzhen 20MWp photovoltaic power generation project is located in Datong, Shanxi, at an elevation of between 1,000 and 1,100 meters. Costing 182.67 million yuan, the project features the use of 260W polycrystalline solar modules and has a design pattern of 20 1MWp photovoltaic sub-units, totaling 20MWp. The outward delivery of the photovoltaic field makes use of the 35kV overhead collector circuit connected to the 35kV bus bar of the 110kV booster station at the China Resources Tianzhen Daliangshan Wind Farm, and the single 110kV circuit from the booster station of the wind farm to the 110kV Tianzhen transformer substation.